A surprising report by Bloomberg claims 16K GB200[1] by summer 2025 at Abilene site (pilot campus of Stargate) and merely 64K GB200 by end of 2026. This is way too little to be a training system, Colossus already has more compute (200K H100/H200) than the projected 64K GB200 at end of 2026.
If this is correct, OpenAI will be training with Azure rather than Stargate in 2025, so raw compute GPT-5 (2e27 FLOPs, 100x GPT-4) probably won't be out in 2025 and officially "GPT-5" will mean something else (since it's due "in months" in any case according to Altman). Also, a datacenter with 16K Blackwells only costs about $1bn, they have more money than this, which suggests Blackwell ramp up trouble that might delay everyone else as well, though as a lower bound Nvidia reported $11bn in Blackwell sales for Nov 2024 - Jan 2025 (it's "Q4 2025" since their FY 2025 runs to end of Jan 2025).
In principle "16K GB200" might mean more Blackwell chips than 16K, a compute tray has more than one chip, with variants marketed as named products like GB200 NVL4 "superchip", but even at 4 chips per tray/board we still get below 200K H100s in compute. And an NVL72 system has 72 chips (which brings the numbers too high). ↩︎
That's indeed inconvenient. I was aware of NVL2, NVL4, NVL36, NVL72, but I was under the impression that 'GB200' mentioned on its own always means 2 Blackwells, 1 Grace (unless you add on a 'NVL__'). Are there counterexamples to this? I scanned the links you mentioned and only saw 'GB200 NVL2,' 'GB200 NVL4,' 'GB200 NVL72' respectively.
I was operating on this pretty confidently but unsure where else I saw this described (apart from the column I linked above). On a quick search of 'GB200 vs B200' the first link I found seemed to corroborate GB200 = 2xB200s + 1xGrace CPU. Edit: second link also says: "the Grace-Blackwell GB200 Superchip. This is a module that has two B200 GPUs wired to an NVIDIA Grace CPU..."
5Vladimir_Nesov
"GB200 superchip" seems to be unambiguously Grace+2xB200. The issue is "100K GB200 GPUs" or "100K GB200 cluster", and to some extent "100K GPU GB200 NVL72 cluster". Also, people will abbreviate various clearer forms to just "GB200". I think "100K chip GB200 NVL72 training system" less ambiguously refers to the number of B200s, but someone unfamiliar with this terminological nightmare might abbreviate it to "100K GB200 system".
Good point, thanks. Previously I would have pretty confidently read "100K GB200 GPUs," or "100K GB200 cluster" as 200K B200s (~= 500K H100s) but I can see how it's easily ambiguous. Now that I think of it, I remembered this Tom's Hardware article where B200 and GB200 are mistakenly used interchangeably (compare the subtitle vs. the end of the first paragraph)...